US 89 scheduled to reopen this month following 2013 landslide, weather permitting

us89_timelapse_above_slide_julythrunov2014PHOENIX — Two years after a landslide ripped apart a 500-foot section of US 89 and split the communities of Bitter Springs and Page, the Arizona Department of Transportation anticipates reopening the highway to traffic on the afternoon of Friday, March 27, barring any potential weather delays or mechanical breakdowns during the paving process, which began today.

Page Unified School District buses are expected to be the first vehicles to pass through newly rebuilt roadway. Students from the Bitter Springs and Marble Canyon areas have been among the most impacted by the US 89 closure, which has remained in place following the Feb. 20, 2013, geologic event approximately two miles north of the US 89/US 89A junction near the community of Bitter Springs.

Following the paving of Temporary US 89 in August 2013, US 89T has served as the detour route for motorists headed to and from the Page and Lake Powell areas, but residents and students in the Bitter Springs and Marble Canyon communities have still had to go out of their way to travel to and from Page and Lake Powell.

“The reopening of Highway 89 is great news for Page Unified School District and the families that we serve in the communities of Marble Canyon, Bitter Springs and Cedar Ridge,” said Page Unified School District Superintendent Jim Walker. “The district will be now be able to re-establish our traditional bus runs to these communities, which will reduce the time that some of these children spend on our buses by up to an hour on a one-way trip. I would like thank our families for their efforts to continue to support their children’s school attendance during this very challenging time.”

Prior to the March 27 reopening, crews will be completing the paving, install rumble strips and guardrail, and add temporary striping and pavement markers along the roadway.

Prior to launching the $25 million repair project last summer, which included removing approximately one million cubic yards of rock material to realign the roadway and construct a downslope rock buttress at the base of the Echo Cliffs to stabilize the area, ADOT had to clear several hurdles to move the project forward.

The ultimate repair of US 89 is the final step in fulfilling ADOT’s three-pronged approach to the US 89 landslide incident, which included providing immediate emergency access, conducting a geotechnical investigation and restoring essential traffic to the area. Paving US 89T (Navajo Route 20) has been the short-term solution for motorists driving to and from Page.

“ADOT recognizes the importance of this corridor and what it means to the communities of Bitter Springs, Cedar Ridge and Marble Canyon,” said ADOT Intermodal Transportation Division Director Steve Boschen. “While the Feb. 20, 2013, landslide event was certainly unexpected and a severe blow to the area, it was a reminder about how critical transportation infrastructure is to the motorists, businesses, local residents and schoolchildren who rely on it every day.”

After an extensive geotechnical assessment identified the necessary repairs in July 2013, ADOT retained an engineering firm and developed plans for the eventual repair; finalized all federally required environmental reviews that included cultural, biological and water quality measures; and completed plans for the required right-of-way easements.

ADOT, along with the Federal Highway Administration, Navajo Nation, Navajo Division of Transportation and the Bureau of Indian Affairs, were able to expedite the environmental, utility and right-of-way clearance process, knowing that the use of US 89T was a temporary fix, especially for the Bitter Springs area communities.

The US 89 landslide repair project is eligible for reimbursement through the Federal Highway Administration’s emergency relief program, which provides funding to state and local agencies for the repair or reconstruction of highways, roads and bridges that are damaged in natural disasters and catastrophic failures.

South Mountain Freeway gains final federal approval

PHOENIX –– The Valley’s Loop 202 South Mountain Freeway, proposed by regional planners since the 1980s, has received final approval from the Federal Highway Administration, paving the way for the Arizona Department of Transportation to move the project forward.

The Record of Decision, signed March 5 by the Federal Highway Administration, grants the final approval necessary for ADOT to begin the process of acquiring right of way, complete the design and begin construction of the 22-mile-long freeway to serve the metro Phoenix region.

The Record of Decision will allow ADOT to begin final design and subsequent construction of the South Mountain Freeway. Acquisition of right of way is expected to begin immediately. ADOT has determined that, pursuant to an unsolicited proposal submitted to construct the freeway, construction will follow a public-private partnership path, helping to speed construction and reduce overall costs. The freeway would not be tolled under any public-private partnership proposal, but would include a private group involved with final design, construction and a 30-year agreement to maintain the freeway.

“The South Mountain Freeway has been approved as a part of two elections that have provided the region with additional transportation funding. Voters recognized the need and the benefits of this project to provide connectivity, travel reliability and route options for a growing region,” said ADOT Director John Halikowski. “Both ADOT and the Maricopa Association of Governments agree this is a critically needed project, and ADOT is breaking new ground by moving it forward under a public-private partnership agreement to more closely involve the private sector, helping to save money and speed construction.”

The proposed South Mountain Freeway has been a critical part of the Maricopa Association of Governments’ Regional Freeway Program since it was first included in funding through Proposition 300, approved by Maricopa County voters in 1985. The freeway was also part of the Regional Transportation Plan funding passed by Maricopa County voters in 2004 through Proposition 400.

The South Mountain Freeway is the last piece to complete the Loop 202 and Loop 101 freeway system necessary for high-quality regional mobility, according to regional planners.

“This is a great day and an important milestone in the history of the Valley’s transportation system,” said Maricopa Association of Governments Chair Michael LeVault, mayor of Youngtown. “It has been a long time coming, and we look forward to the improved mobility and economic opportunities that this freeway facility will bring to our region.”

The environmental review process, which included preparing both draft and final environmental impact statements, was conducted in accordance with the National Environmental Policy Act and identified the preferred route for this freeway corridor – running east and west along Pecos Road and then north and south between 55th and 63rd avenues, connecting with Interstate 10 on each end. The Final Environmental Impact Statement documented the analysis of potential impacts associated with the freeway and the no-build alternative, and addressed comments received on the draft and final Environmental Impact Statements. The draft environmental report was published in 2013, followed by publication of the Final Environmental Impact Statement in 2014.

The Federal Highway Administration has decided to identify the Preferred Alternative (a combination of the W59 and E1 Alternatives) as the Selected Alternative for the South Mountain Freeway project. This decision along with supporting information, including responses to public comments received on the Final Environmental Impact Statement, is documented in the Record of Decision.

The freeway will be constructed with four lanes in each direction – three general-use lanes and one HOV lane – and modern features that have made Arizona freeways stand apart from other states for a generation, including rubberized asphalt and aesthetics designed in partnership with the community. The $1.9 billion project is expected to take about four years to construct.

60-day ramp closures start Mar. 9 at the Loop 101/Thomas Road interchange

PHOENIX — As part of the Loop 101 Improvement Project in the East Valley, additional on- and off-ramps will be closed for approximately two months starting Monday (March 9), according to the Arizona Department of Transportation.

The northbound Loop 101 on- and off-ramps at Thomas Road are scheduled to close by early Monday morning. Crews will reconstruct the ramps so they fit into the path of the wider freeway. The ramps are due to reopen by mid-May.

Drivers are encouraged to use ramps at other nearby interchanges along Loop 101 while the ramps at Thomas Road are closed.

The work is part of the $73 million project to add new right lanes along Loop 101 between Shea Boulevard and Loop 202 (Red Mountain Freeway). The entire project is scheduled for completion next year.

The northbound Loop 101 on-ramp and southbound off-ramp at McKellips Road were closed to traffic last week. They are scheduled to reopen by early May.

Project schedules are subject to change due to inclement weather.

Overnight pipe installation scheduled on SR 89 in Chino Valley on Sunday

Pipe installation is scheduled on northbound State Route 89 near Windy Valley Plaza in Chino Valley on Sunday night, March 8 between 8 p.m. and 5 a.m. Drivers can expect minimal delays during work hours.

Law enforcement personnel will be present and drivers are encouraged to adhere to the reduced speed limit and be alert for construction equipment and personnel.

The work zone will be clearly marked by temporary barricades and signage. Note that Arizona Revised Statue allows for double the fine for speeding through a construction zone.

Traffic shift scheduled on Monday on SR 89 at Road 4 North in Chino Valley

CHINO VALLEY – Traffic will be shifted onto the new temporary detour on the east side of State Route 89 at Road 4 North on Monday, Feb. 23. Drivers in both directions will be shifted onto the detour for the next six months as crews begin constructing the new roundabout at the intersection.

The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to allow additional time to reach their destinations and to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

This $2.1 million project consists of a new roundabout at the intersection of SR 89 and Road 4 North between mileposts 330.48 and 330.78. Additional work includes removal and replacement of existing pavement, drainage improvements, new pavement markings and lighting.

This project is expected to be complete by August.

ADOT continues efforts to upgrade US 93 corridor

PHOENIX — The Arizona Department of Transportation launched a new project this week to widen US 93, the primary travel route for Phoenix drivers headed to Las Vegas, and efforts continue on another ongoing widening project to further a decades-long commitment to convert the rural two-lane roadway to a modern, four-lane divided highway in northwest Arizona.

Just north of Wickenburg, ADOT started this week on the expansion of US 93 between State Route 71 and State Route 89 (mileposts 185-190). The $12.5 million project, reconstructing the highway into four lanes, is expected to be completed in 2016.

This project will be funded through the Federal Highway Administration’s Highway Safety Improvement Program.

Along this section of highway, ADOT previously installed a centerline rumble strip, which is a pattern of small cuts in the pavement, in an effort to alert drivers whose vehicles cross the centerline of the two-lane, two-way roadway. Signs were also added to remind drivers that US 93 has two-way traffic and ADOT made it a requirement that drivers use their headlights during daylight hours.

“Safety has been the drive force behind our series of projects to convert US 93 into a divided four-lane highway,” said ADOT State Engineer Dallas Hammit. “ADOT’s long-term goal is to have a modern, four-lane divided highway between Phoenix and Las Vegas and we’ll continue to get closer to that goal as funding becomes available.”

Approximately 80 miles north of the project near Wickenburg, ADOT is continuing work on widening the Antelope Wash segment of US 93 (mileposts 101-104), roughly 20 miles north of Wikieup.

The $20 million improvement project began last summer and crews are currently reconstructing the future northbound lanes of US 93, which are adjacent to the existing US 93 alignment. The widening project, which is nearly 70 percent completed, is slated to be finished this summer.

ADOT urges drivers to proceed through the work zones with caution, slow down, and be alert for construction equipment and personnel.

Since 1998, ADOT has invested approximately $350 million in projects to upgrade the US 93 corridor, which stretches from Kingman to the Nevada state line and Wickenburg to Interstate 40 (a 23-mile segment of I-40 east of Kingman connects the north and south sections of US 93).

Currently, all but 49 miles of the 200-mile drive (more than 75 percent) from Wickenburg to the Nevada state line has been upgraded to a four-lane divided highway in an effort to improve traffic flow, support the movement of freight and enhance safety through this heavily-traveled area. The entire northern segment of US 93 from Kingman to the Nevada state line (mileposts 1-68) is now a four-lane divided highway following the completion of a $71 million project in 2010.

When the SR 71 to SR 89 and Antelope Wash sections are completed, ADOT will have widened an additional eight miles of the 109-mile stretch of US 93 from Wickenburg to I-40.

Ultimately, US 93 could become part of the proposed Interstate 11 corridor that, once fully constructed, would connect Nogales and Las Vegas, extending north through Nevada, potentially reaching as far as Canada.

Last October, ADOT and the Nevada Department of Transportation completed the I-11 and Intermountain West Corridor Concept Report, the final element in the initial two-year feasibility study, this document can be found at www.i11study.com.

“US 93 has been designated as a potential alignment for the proposed Interstate 11 corridor,” said ADOT Director John Halikowski. “With the continued growth in the southwest, it’s essential that we have the transportation infrastructure in place to accommodate the efficient movement of goods and motorists in Arizona, and to support the movement of freight beyond our borders.”

Widening project has begun on US 93 west of Wickenburg

PRESCOTT – The Arizona Department of Transportation launched a new project this week to widen US 93, the primary travel route for Phoenix drivers headed to Las Vegas, and efforts continue on another ongoing widening project to further a decades-long commitment to convert the rural two-lane roadway to a modern, four-lane divided highway in northwest Arizona.

Just north of Wickenburg, ADOT started this week on the expansion of US 93 between State Route 71 and State Route 89 (mileposts 185-190). The $12.5 million project, reconstructing the highway into four lanes, is expected to be completed in 2016.

This project will be funded through the Federal Highway Administration’s Highway Safety Improvement Program.

Along this section of highway, ADOT previously installed a centerline rumble strip, which is a pattern of small cuts in the pavement, in an effort to alert drivers whose vehicles cross the centerline of the two-lane, two-way roadway. Signs were also added to remind drivers that US 93 has two-way traffic and ADOT made it a requirement that drivers use their headlights during daylight hours.

I-15 bridge improvement work progresses along Virgin River Gorge

virginriverbridgePHOENIX — As progress continues on the reconstruction of Virgin River Bridge No. 6, the Arizona Department of Transportation is urging motorists traveling on Interstate 15 between Mesquite, Nevada, and St. George, Utah, to plan ahead for construction delays up to 20 minutes next week.

Beginning on Monday, Feb. 23, crews will install the girders on the new southbound bridge structure.

This work, which will continue through the end of March, will require intermittent rolling lane closures to allow for the safety of both construction crews and the traveling public. Work hours will be Monday through Thursday from 6 a.m. to noon.

For more information on the intermittent traffic breaks that will occur, watch the following ADOT YouTube video: http://youtu.be/FyUcqpQCfig.

While one travel lane will remain open in each direction, motorists are reminded to slow down and drive carefully through the work zone and be alert for construction equipment and personnel.

The $27 million rehabilitation of Virgin River Bridge No. 6 (milepost 16) began in March 2014, and is anticipated to be complete in 2016. This significant project includes the replacement of the bridge’s superstructure (girders, deck and railings), as well as widening the roadway through the narrow passage of the Virgin River Gorge.

Drivers should allow for up to 15 minutes extra travel time during regular construction activities occurring on weekdays from 6 a.m. to 6 p.m. Additional delay time may occur on weekends due to heavier traffic volume and special events.

The busiest travel time through the Gorge is Friday through Sunday. With limited alternate routes due to the remote location of the I-15 Virgin River Gorge corridor, ADOT urges drivers to plan ahead and allow extra travel time.

ADOT works to inform the public about planned highway restrictions. Unscheduled restrictions or closures may occur. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at az511.gov or call 5-1-1; outside Arizona, dial 1-888-411-ROAD (7623).

For more information about the I-15 Virgin River Gorge projects, please visit azdot.gov/I15virginriver.

ADOT MVD offers online vehicle license tax report for 2014

PHOENIX – As Arizonans start working on their tax returns, many want to know the amount of vehicle license tax they paid last year.

The Arizona Department of Transportation Motor Vehicle Division offers a free online service, Vehicle Fee Recap, on ServiceArizona.com to help vehicle owners easily obtain their vehicle license tax paid in 2014 as well as any specialty license plate donations.

From the ServiceArizona home page, a customer can select the Vehicle Fee Recap link and follow the simple instructions to receive a free, printable report. The Vehicle Fee Recap report will only contain information for the previous calendar year.

“Vehicle Fee Recap has proven to be one of ServiceArizona’s most popular features during tax season,” said Motor Vehicle Division Director Stacey Stanton. “This service is yet another way MVD works to save valuable time for our customers.”

Owners of Arizona-registered vehicles who wish to use the data provided in the Vehicle Fee Recap report for tax returns should seek guidance from the Internal Revenue Service, the Arizona Department of Revenue or other tax professionals.

The Vehicle Fee Recap feature of ServiceArizona is also accessible by mobile devices.

Sidewalk repairs on US 60 and Tegner Street in Wickenburg this week

WICKENBURG – Arizona Department of Transportation maintenance crews are scheduled to repair the curb and sidewalk on US 60 and Tegner Street in Wickenburg starting on Tuesday, Feb. 17.

Westbound US 60 will be narrowed to one lane approaching the intersection and parking along the sidewalk through the work zone will not be permitted.

Drivers will be allowed to turn right onto Tegner Street from US 60 by using the left lane through the work zone.

Work hours are from 7 a.m. to 5 p.m. Tuesday through Friday and work is expected to be complete by Friday, Feb. 20.