Cactus Asphalt Williams work schedule

Chip sealing on west end through Country Club Road completed yesterday.

WILLIAMS – Cactus Asphalt passed out flyers, yesterday, concerning the chip seal project they are working on. There is currently no plan to work on Route 66 proper. They are working on the cross-roads and work began today. Tomorrow they will be working from the Mustang station east toward ADOT. Cones and pilot vehicles will be used for worker safety.

They don’t actually have a pilot “car.” It’s more of a pilot truck.

The process begins with cleaning the roads, spraying oil and chip seal and leaving it overnight. The next day they re-clean the area and open it up. They will be working from 6 a.m. to 6 p.m.

Thursday and Friday they will be chip sealing the two-mile stretch from Santa Fe dam to Dogtown Road. One lane will be open for traffic. They ask that you follow the directions of construction workers and wait for pilot vehicle